To delay a task:
  1. In the left pane, on the Automations tab, click Tasks.
    The Tasks pane is displayed.
  2. Click next to the task you want to delay and then click Delay .
    The Delay task dialog box is displayed.
  3. Enter a new date and time and then click Delay task.