The staging of Export Packages is scheduled from the OnBase Client and will automatically stage packages at the days/times configured. To configure a staging schedule:

  1. Select Document Transfer | Processing Console from the Processing menu of the OnBase Client. The Document Transfer Processing Console dialog is displayed.
  2. Right click Document Transfer Processor in the right hand pane and select Schedule Format to schedule the processor to run at the days/times configured.
  3. See the Scheduling appendix in this manual for complete details on configuring a Schedule Format (Creating a Scheduled Process Format).
    Note:

    The Schedule Commit option is not used by Document Transfer.