A Keyword Update process can be scheduled to run as an automated process. To schedule a Keyword Update process, a preprocessor must be run against the index file. If the Schedule Format option is unavailable, the selected process needs to be configured to use a preprocessor. See Preprocess Options for more details. The workstation will need to be running with the -SCHED command line switch in order to run a scheduled process. To schedule a Keyword Update process:

  1. From the Keyword Update window, click on the process you want to schedule.
  2. Right-click and select Schedule Format. The Schedule Management window is displayed.
  3. Select the Scheduling options you want to use. For more information, see Scheduling Overview.
  4. Click Apply.
  5. Click OK.