Scheduled processes can be deleted from the Schedule Management window.

  1. Open the Schedule Management window in one of the following ways:
    • Right-click in the Document Maintenance window and select Schedule Purge.

    • From the OnBase Client, click Processing | Scheduler | Schedule Management.

    Note:

    Users without the Utilities product right will not be able to view document purge scheduled processes from the Schedule Management window.

  2. Select the scheduled process you would like to delete from the Scheduled Items dialog box and click Remove.
    Tip:

    If you accessed the Schedule Management window from the Document Maintenance window, a new scheduled process was automatically created. If you have no plans to create a new scheduled process, it should be removed.

  3. Click Apply.