Copy a path for an advanced policy - Retention Policy Designer - Foundation 24.1 - Foundation 24.1 - Ready - Perceptive Content - external - Perceptive-Content/Retention-Policy-Designer/Foundation-24.1/Retention-Policy-Designer/Retention-Policy-Designer-Online-Help/Work-with-paths/Copy-a-path-for-an-advanced-policy - 2024-04-02 - To copy a path in an advanced policy that is not activated, complete the following steps.

Retention Policy Designer

Platform
Perceptive Content
Product
Retention Policy Designer
Release
Foundation 24.1
License

To copy a path in an advanced policy that is not activated, complete the following steps.

  1. In Retention Policy Designer, perform one of the following procedures.
    Policy Layout Steps
    Your policy contains a single phase and multiple paths
    • In the Paths column, select the path you want to copy.
    Your policy contains multiple phases
    1. In Retention Policy Designer, in the Phases column, select the phase that contains the path you want to copy.
    2. In the Paths column, select the path you want to copy.
  2. Click Edit > Copy.