Modify time rules - Retention Policy Designer - Foundation 24.1 - Foundation 24.1 - Ready - Perceptive Content - external - Perceptive-Content/Retention-Policy-Designer/Foundation-24.1/Retention-Policy-Designer/Retention-Policy-Designer-Online-Help/Work-with-paths/Use-time-rules/Modify-time-rules - 2024-04-02 - To modify the time rule in a simple or advanced policy, complete the following steps.

Retention Policy Designer

Platform
Perceptive Content
Product
Retention Policy Designer
Release
Foundation 24.1
License

To modify the time rule in a simple or advanced policy, complete the following steps.

The Paths column displays only when more than one path is defined.
  1. In Retention Policy Designer, perform one of the following procedures depending on your policy type. Simple policies do not have multiple phases, so if you are using a simple policy, skip this step.
    Policy Layout Steps
    Your policy contains a single phase and multiple paths
    • In the Paths

      column, select the path that contains the time period you want to modify.
    Your policy contains multiple phases
    1. In the Phases column, select the phase that contains the path you want to modify.
    2. In the Paths column, select the path that contains the time period you want to modify.
  2. Under Details, on the Time Period tab, in the Date type list, select a date.
  3. Click File > Save.